226·2023年9月工程技术与应用江西建材管线综合布置技术在机电安装工程中的应用探戴泽林福建省二建建设集团有限公司,福建福州350001摘要:文中以福州某建筑工程项目为例,从管线布置、一级管线布置、二级管线布置、三级管线布置等四个方面,阐述了管线综合布置原则,分析了管线综合布置技术应用要点,包括施工前准备、设计管线综合布置图、截取管线、绘制管线综合剖面图、管线综合布置方案支吊架优化、其他技术要点等,并阐述了管线综合布置技术应用保障措施。关键词:管线;综合布置技术;机电安装中图分类号:TU81文献标识码:B文章编号:1006-2890(2023)09-0226-03ApplicationofPipelineComprehensiveLayoutTechnologyinMechanicalandElectricalInstallationEngineeringDaiZelinFujianSecondConstructionGroupCo.Ltd.,FuzhoFujian350001Abstract:TakingacertainengineeringprojectinFuzhouasanexample,thearticleelabo.atesontheprinciplesofcomprehensivepipelinelayoutfromfouraspects:pipelinelayout,firstlevelpipelinelayout,secondlevelpipelinelayout,andthirdlevelpipelinelayout.Itanalyzestheapplicationpointsofcomprehensivepipelinelayouttechnology,includingpreconstructionpreparation,designofcomprehensivepipelinelayoutdiagram,pipelineinterception,drawingofcomprehensivepipelineprofilediagram,optimizationofpipelinecomprehensivelayoutplansupportandhanger,andothertechnicalpoints.Atthesametime,theapplicationguaranteemeasuresforcomprehensivepipelinelayouttechnologywereelaborated.Keywords:Pipeline;Comprehensivelayouttechnology;Mechanicalandelectricalinstallation0引言机电安装工程管线综合布置质量直接影响管线和设备的后期维护和整体观感,进而影响施工质量。本文以福州某工程项目为例,在明确管线综合布置原则的基础上,借助Revit建模平台,使用AutoCAD、Navisworks、3dsMax、Lumion等辅助软件,进行二维图纸修改、碰撞和审阅、施工模拟动画、漫游动画制作等,对项目机电安装施工管线综合布置技术的应用进行详细阐述分析;通过精细化建模、图纸会审、碰撞检查、净高分析等技术手段对设备机房、消控中心、配电间、管道井、屋面设备、智能化设备、预留孔洞和支吊架布置进行综合优化,提出了管线综合布置技术应用保障措施。1工程概况福州某建筑为框架结构,总建筑面积为63326.82m²,由7栋建筑、...