2022·12·BuildingConstruction2908高空遮阳膜预应力张拉分块吊装施工技术郝加生欧传超冯井方敖开银于巧巧江奎杨子旭华鼎建筑装饰工程有限公司上海200333摘要:结合萧山国际机场三期交通中心工程,对高空遮阳膜跨越障碍吊装施工技术进行了研究。通过对施工难点及安全风险点进行分析,在施工过程中对垂直吊装和跨越障碍后的平行移动路线进行规划,最终顺利完成了施工,总结的经验可为类似项目提供参考。关键词:遮阳膜;跨越障碍;分板块吊装;装配式安装中图分类号:TU755文献标志码:A文章编号:1004-1001(2022)12-2908-04DOI:10.14144/j.cnki.jzsg.2022.12.029ConstructionTechnologyofPrestressedTensioningandBlockHoistingofHighAltitudeSunshadeFilmHAOJiashengOUChuanchaoFENGJingfangAOKaiyinYUQiaoqiaoJIANGKuiYANGZixuHuadingConstructionDecorationEngineeringCo.,Ltd.,Shanghai200333,ChinaAbstract:CombinedwiththethirdphasetrafficcenterprojectofXiaoshanInternationalAirport,thehoistingconstructiontechnologyofhigh-altitudesunshadefilmspanningobstaclesisstudied.Throughtheanalysisofconstructiondifficultiesandsafetyriskpoints,theverticalliftingandparallelmovementrouteaftercrossingobstaclesareplannedduringtheconstructionprocess,andtheconstructionissuccessfullycompleted.Theexperiencesummarizedcanprovidereferenceforsimilarprojects.Keywords:sunvisor;crossingobstacle;hoistingbyplate;assembledinstallation1工程概况杭州萧山国际机场三期项目是2022年杭州亚运会保障工程,萧山国际机场三期交通中心工程是目前全国机场类在建规模最大的GTC综合交通换乘中心,总建筑面积64万m2,建成后将实现与高铁、地铁、大巴的无缝换乘,届时萧山国际机场将成为一个亚太门户枢纽和国家综合交通枢纽。高空遮阳膜预应力张拉分块吊装施工位于中庭2—14轴与2—15轴之间,属于交通中心核心位置,由16块等分扇形组成,相邻板块之间间距0.5m,安装完成后整体呈圆形。高空遮阳膜安装标高为30m,位于钢结构梁与预应力连杆之间,与地面呈15°夹角,膜完成面到钢结构梁及预应力连杆距离均为0.75m。该区域高度大、空间小且遮阳膜位于预应力连杆之上(图1),不能采用传统安装、吊装方式,施工难度大且安全风险系数高,需考虑遮阳膜应力张拉及高空吊装的可靠性,采用“预应力张拉+分块吊装”的形式,保证遮阳膜预应力张拉的可...