甘特图查看说明查看说明工程进度表工程进度表任务开始时间持续时间结束时间基础土方开挖41800141801室外围墙418006141861官网外排水41800104181041802041802基础钢筋绑扎41803241805路面、路灯、绿化418055641861基础模板安装41806241808内外墙体砌筑418073041837浇捣基础砼41810341813一层结构模板安装41810241812一层结构钢筋绑扎41813241815二层楼面浇捣砼41816041816二层结构模板安装41817241819二层结构钢筋绑扎41819141820内墙体抹灰418202041840外墙体抹灰418202041840屋面防水、保温418201041830三层楼面浇捣砼41821041821卫生洁具418214041861铝合金外窗框418211441835内门框扇418214041861三层结构模板安装41822241824三层结构钢筋绑扎41824241826四层楼面浇捣砼41827241829屋面花格制作安装41829341832卫生间墙面砖418301541845外墙涂料418351041845楼地面找平层418351041845卫生间地砖418351541850外墙脚手架搭设至拆除418402141861内墙刮腻子418401641856室内复合木地板418521441866铝合金窗扇41856541861楼梯栏杆护手41856541861C15砼垫层基础土方开挖C15砼垫层基础模板安装一层结构模板安装二层结构模板安装外墙体抹灰卫生洁具三层结构模板安装屋面花格制作安装楼地面找平层内墙刮腻子楼梯栏杆护手14/06/0614/06/1614/06/2418004180041800418024180341805418064180741810418104181341816418174181941820418204182041824182418241824184418014181041802418054180841814181241841工开挖垫层安装安装安装抹灰洁具安装安装平层腻子护手4/06/0614/06/1614/06/2614/07/0614/07/1614/07/2614/08/0514/08/154180041800418004180241803418054180641807418104181041813418164181741819418204182041820418214182141821418214182241824418274182941830418354183541835418404184041852418564185641801418614181041802418054186141808418374181341812418154181641819418204184041840418304182141861418354186141824418264182941832418454184541845418504186141856418664186141861工程进度表使用前请检查宏是否启用数据可以任意更改,但是确保数据在A1单元格上任务开始时间持续时间结束时间基础土方开挖41800141801室外围墙418006141861官网外排水418001041810C15砼垫层41802041802基础钢筋绑扎41803241805路面、路灯、绿化418055641861基础模板安装41806241808内外墙体砌筑418073041837浇捣基础砼41810341813一层结构模板安装41810241812一层结构...