17848ba7d22f2465152e1c6e6747c031.xlsGattgraph-001第1頁,共1頁项目实施进度安排项目开始时间:5/26/2009序号任务名称计划工时开始时间计划完成时间实际完成日期实际工时图表数据滞后时间1设备到货签收1.05/26/20095/26/20095/26/20091.0###0.00.02设备到货验收1.06/1/20096/1/20096/17/200917.0###16.03设备上架2.06/2/20096/3/20096/3/20092.0###0.00.043.06/4/20096/6/20096/6/20093.0###0.00.05主机房存储配置及调试2.06/4/20096/5/20096/5/20092.0###0.00.06主备机房光缆施工6.06/6/20096/14/20096/14/20096.0###0.00.07备用机房储配置及调试1.06/15/20096/15/20096/15/20091.0###0.00.082.06/15/20096/16/20096/15/20091.0###1.092.06/17/20096/18/20096/18/20092.0###0.00.0102.06/17/20096/18/20096/19/20093.0###1.0114.06/19/20096/24/2009###124.06/19/20096/24/20096/25/20095.0###1.0132.06/25/20096/26/2009142.06/25/20096/26/2009###15机房迁移2.06/26/20096/27/2009###163.06/29/20097/1/2009173.06/29/20097/1/2009###18网络实施8.06/8/20096/17/2009###19项目验收4.07/1/20097/4/2009计划进度提前完成延期报告人:提前完工时间服务器安装(WinorHP-UX)VCS集群安装配置(ForWinorHp-ux)Sybase数据库安装Sqlserver数据库安装Sybase迁移测试Sqlserver迁移测试Sybase数据库迁移Sqlserver数据库迁移Veritas镜像软件安装配置VeritasNBU备份软件安装配置图例:5月26日5月29日6月1日6月4日6月7日6月10日6月13日6月16日6月19日6月22日6月25日6月28日